• Capital Improvement List for 2018 – 2022

     

    Priority

    Project

    Description/Rationale

    Estimated Cost in $

    Projected Timeline

     

    New Collinsville Elementary

    Construct new elementary school to combine Collinsville Primary and John Redd Smith Elementary along with Special Education programming from Stanleytown Elementary. 

    22,000,000

    Completed 

    (Meadow View Elementary opened in 2018)

    1.  

    Pupil Transportation – new facility

    HCPS has acquired a property for the new Pupil Transportation facility and has received drawings for the site-work to be completed at the new location. 

    1,620,000

    Ongoing 

    (Site-work will continue in FY 2022)

    2.

    Bassett High School Greenhouse

    New greenhouse attached to the existing building at Bassett High School.

    450,000

    2021 (Start)

    Project in Design

    3

    G.W. Carver Elementary Kitchen/ Storage renovation and addition

    Kitchen and storage addition – to replace modular buildings. This is the smallest kitchen in the school division, and it serves one of the largest elementary school populations in the school division.

    1,080,000

    2021 (Start)

    Project in Design Phase

    Bassett High School HVAC System, Ceiling, and Lighting Replacement

    Replace deteriorated 1978 HVAC system, excluding existing chillers. While chillers at Bassett were replaced in the 1990s and in 2002, air handlers, variable air volume units, and most of the controls are original equipment and are deteriorated from use and age. Project includes adding air conditioning for gymnasium and kitchen.

    3,189,000

    2022 (Start)

    May apply CARES Funding for HVAC portion of work

    5a, 5b

    Field Houses at Bassett High School and Magna Vista High School

    Both high schools need athletic field houses near the football/soccer fields. This is for the safety of the students participating in the athletic contests. 

    750,000

    2022 (Start)

    May apply 1% Sales Tax Revenue

     

    Axton Elementary and Rich Acres paving improvements

    Front parking lots need repairs to maintain a safe parking and driving area. 

    225,000

    Completed

    in 2019

     

    Axton Elementary – Replace Variable Air Volume boxes and controls

    VAV boxes currently have pneumatic controls and are out of date. These need to be replaced with new Direct Digital Controls boxes for better control of the environment.

    325,000

    Completed 

    in 2020

     

    BHS Bathroom Renovations

    Bathrooms need to be upgraded for better handicap accessibility

    525,000

    Completed

    in 2019

     

    Transportation Garage Roof Replacement

    Replace existing roof with new, fully-adhered 60-mil EPDM with tapered average R21 insulation

    143,640

    Removed 

    with purchase of new facility for Transportation

     

    Renovate the Center for Community Learning

    Renovate by replacing HVAC, lighting, finishes, doors and hardware, windows, toilets, etc. HVAC system and windows are very inefficient. These renovations are recommended with the understanding that the Career Academy will occupy the old Figsboro Elementary School, formerly home of CCL. 

    2,430,000

    Removed from list

    in 2019. 

    Renovations at Career Academy have been ongoing

     

    Bassett High School Roof Replacement

    Existing coating warranty will expire and the roof is due for replacement

    2,690,000

    Completed 

    in 2020

     

    Drewry Mason Elementary covered walkway

    Construct covered walkway for bus and car rider loops. This will help to keep children and staff out of weather during arrival and dismissal times

    216,000

    Removed from list for equity reasons

    6.

    Laurel Park Middle School – Replace HVAC rooftop units and roof replacement

    The normal life expectancy of a rooftop A/C unit is 18 years. In 2020, the rooftop units will be approximately 20 years old and due for replacement. The existing roof will need to be replaced with new EPDM roof in a similar timeframe. 

    5,000,000

    2022 (Start)

    May apply CARES Funding for HVAC portion of work

    7.

    Sanville Elementary Renovation and Addition

    Construct new classroom additions to replace the 1927 original structure and discontinue the use of mobile units, develop teacher support/resource areas, improve traffic flow and parking, renovate older areas of the building, and enlarge/ renovate the kitchen. 

    6,500,000

    Beyond 2022

    8a, 8b, 8c, 8d

    All secondary schools – Install generators

    Bassett High School, Magna Vista High School, Fieldale-Collinsville Middle School, and Laurel Park Middle School could be used for a community emergency, and these schools currently do not have onsite generators for backup lights or refrigeration online. 

    725,000

    (estimate reflects total cost)

    Beyond 2022

    Potential for Grant Funding

    9a, 9b, 9c

    Rich Acres/Sanville/ Fieldale-Collinsville Middle School – Chiller replacement

    The normal life expectancy of air-cooled chillers is 20 years. In 2020, all of the listed chillers will have reached their life expectancy and will be due for replacement.

    600,000

    (estimate reflects total cost)

    Beyond 2022

    May apply CARES Funding for HVAC portion of work

    10a, 10b, 10c

    Drewry Mason, Campbell Court, and GW Carver Elementary schools – Handicap accessible upgrades

    Installation of elevator lifts for access to multiple levels and ramps 

    500,000

    (per site)



    Beyond 2022

    Elevator at Fieldale-Collinsville Middle School was added in 2020, so this site has been removed (completed)

    11.

    FCMS gymnasium and kitchen air conditioning

    Add A/C systems for the gymnasium and kitchen at Fieldale-Collinsville Middle School

    540,000

    Beyond 2022

    12.

    LPM gymnasium air conditioning

    Add A/C system for the gymnasium at Laurel Park Middle School

    440,000

    Beyond 2022