Capital Improvement List

Project

Site(s)

Notes

1

HVAC System Replacement; Ceiling Replacement; Lighting Replacement

Bassett High School

Estimated cost $6.9M

(Areas “A” and “B”: $3.5M)

(Area “C”: $3.014M)

Construction on Area C will take place during summer break at conclusion of 2022-2023 school year.

2

Elevator Installation

George Washington Carver Elementary; Drewry Mason Elementary; Campbell Court Elementary

GWCE estimated cost: $779,000

 

DME estimated cost: $644,000

 

CCE estimated cost: $810,000

3

Rooftop HVAC System Replacement and Roof Replacement

Laurel Park Middle School

Estimated cost of HVAC system replacement: $4M

(Project in design phase)

 

Estimated cost of roof replacement: $4M

4

Field House

Bassett High School; Magna Vista High School

Estimated cost for BHS: $1.21M

 

Estimated cost for MVHS: $1.65M

 

(Projects in design phase)

5

HVAC System Replacements

Multiple sites

RAE estimated cost $2M

STE estimated cost $2.5M

SE estimated cost $2M

FCMS estimated cost $4.5M

7

Locker Room HVAC Installation

Fieldale-Collinsville Middle School

Estimated cost $1.5M

(Project previously put out for bid)

8

Improvements to Athletic Campus and  Handicap Accessibility

Magna Vista High School

No estimate available at this time; some aspects will be achieved through construction of field house

9

Artificial Turf Installation and Track Repair/Replacement

All Secondary Schools 

BHS Track and Turf

MVHS Track and Turf

FCMS Track Only

LPMS Track Only