Capital Improvement List
Project |
Site(s) |
Notes |
|
1 |
HVAC System Replacement; Ceiling Replacement; Lighting Replacement |
Bassett High School |
Estimated cost $6.9M (Areas “A” and “B”: $3.5M) (Area “C”: $3.014M) Construction on Area C will take place during summer break at conclusion of 2022-2023 school year. |
2 |
Elevator Installation |
George Washington Carver Elementary; Drewry Mason Elementary; Campbell Court Elementary |
GWCE estimated cost: $779,000
DME estimated cost: $644,000
CCE estimated cost: $810,000 |
3 |
Rooftop HVAC System Replacement and Roof Replacement |
Laurel Park Middle School |
Estimated cost of HVAC system replacement: $4M (Project in design phase)
Estimated cost of roof replacement: $4M |
4 |
Field House |
Bassett High School; Magna Vista High School |
Estimated cost for BHS: $1.21M
Estimated cost for MVHS: $1.65M
(Projects in design phase) |
5 |
HVAC System Replacements |
Multiple sites |
RAE estimated cost $2M STE estimated cost $2.5M SE estimated cost $2M FCMS estimated cost $4.5M |
7 |
Locker Room HVAC Installation |
Fieldale-Collinsville Middle School |
Estimated cost $1.5M (Project previously put out for bid) |
8 |
Improvements to Athletic Campus and Handicap Accessibility |
Magna Vista High School |
No estimate available at this time; some aspects will be achieved through construction of field house |
9 |
Artificial Turf Installation and Track Repair/Replacement |
All Secondary Schools |
BHS Track and Turf MVHS Track and Turf FCMS Track Only LPMS Track Only |