Forward

This Capital Improvement Plan (CIP) provides a recommended framework for undertaking major capital improvements over the next several years. The following goals continue to guide planning and prioritization of the CIP.

1. Provide a safe, healthy, and inviting learning environment for students, staff, parents, and community.

2. Protect infrastructure and ensure the proper operation of all critical building systems.

3. Ensure that facilities are energy efficient.

4. Ensure that facilities are equipped for current instructional and administrative technologies.

Identifying facilities needs are based on input from principals and administrators, facilities staff, and a range of consultants in the field. In 2021, Cornett & Cundiff, Inc. performed a survey of the roofs in the school division. In 2022-2023, Crabtree, Rohrbaugh & Associates completed a full facilities assessment to identify structural, mechanical, electrical, and plumbing needs for all school sites and assist with capital planning.

From the list of needs, seventeen major projects costing over $100,000 are included in the current CIP. As a caution, estimates should be considered place holders. The best estimates are obtained after preparation of working drawings (bid) documents and true cost is determined through the competitive bid process.

Timelines

The following timelines are hypothetical and predicated on the assumption that the division will increase its Facilities Category over each of the next several fiscal years. The following tables provide a description of projects, costs, and recommended timelines for each project. In some cases, projects are bundled for similar types of work or because of advantages related to logistics.

CAPITAL IMPROVEMENT PLAN LIST

Priorities

Project

Description/Rationale

Cost 

Year

Current Project 

BHS Phase 7 HVAC, lighting, and ceiling replacement

Over many years, we have been working toward replacement of the 1978 HVAC system at BHS to include replacement of the ceiling and lighting.  This would be the final phase of the building to get all of this equipment updated. 

$4,542,000      

1% sales tax

2024

Current Project

LPMS select HVAC replacement 


 

The normal life expectancy of rooftop A/C units is 18 years. Many of the existing units are pushing 30 years old and due for replacement. The outdoor air intake code requirements have changed, so this will improve the indoor air quality of our facility.

$3,195,238 Facilities Budget and CSLFRF Grant

2024

Current Project

RAE and STE HVAC Replacement & Axton Elementary Chiller Replacement 

The HVAC equipment in both of these schools has exceeded it’s life expectancy and in need of replacement. This update would also improve the learning environment with updates to the indoor air quality. 

$4,303,000 

ESSER III and 

1% sales tax

2024

Current Project

Elevator Installation CCE, DME, GWCE

We currently have (3) elementary schools that are multi-level. Installing elevators would give students and staff access to each level while bringing the building to ADA compliance.

Estimated $3,200,000       

 1% sales tax

2024 & 2025

Current Project

Field Houses BHS and MVHS

Constructing athletic field houses at both high schools will improve the facility use while improving safety measures for students using the fields.


 

Estimated $4,000,000      

  1% sales tax

2024

 

Current Project





 

All Elementary Schools 

Adding new inclusive playground equipment to meet the needs of all students at every elementary school with improvements to the playground surface for better access.

Estimated

$1,200,000

ESSER III 

FY24 Budget     

2024


 
 

Total estimated cost for projects in process



 

$20,440,238








 

1.

Roof replacement LPMS

The roof at Laurel Park Middle is currently out of warranty and in need to replacement



 

$3,300,000       

2025

2.

HVA Replacement FCMS

The HVAC equipment at Fieldale-Collinsville Middle School has exceeded it’s life expectancy and in need of replacement. This update would also improve the learning environment with updates to the indoor air quality. 



 

$5,900,000      

2025

3.

HVAC Replacement SE

The HVAC equipment at Sanville Elementary has exceeded it’s life expectancy and in need of replacement. This update would also improve the learning environment with updates to the indoor air quality. 



 

$2,250,000       

2025

4.

Switchgear replacements FCMS and LPMS

The main electrical switchgear is existing from when the school was built and in need of replacement at Fieldale-Collinsville Middle and Laurel Park Middle



 

$3,250,000        

2025

5.

Pavement Replacement STE and CA

The pavement in the parking lots of Stanleytown Elementary and Career Academy is in need of replacement



 

$1,500,000       

2025


 
 

Total estimated cost for FY 2025

$16,200,000









 
 

1.

Roof coating/replacement AE

The roof at Axton Elementary has exceeded its warranty and in need of a new coating on part of the roof and replacement on the other areas.



 

$750,000          

2026

2.

Pavement Replacement FCMS and LPMS

The pavement in the parking lots of Fieldale-Collinsville Middle and Laurel Park Middle is in need of replacement


 

$2,750,000      

2026

3.

Switchgear replacements BHS and MVHS

The main electrical switchgear is existing from when the school was built and in need of replacement at Bassett High and Magna Vista High



 

$3,250,000    

2026

4.

Boiler Replacement MVHS, LPMS, CCE, and AE

The boilers at the listed facilities are 30 plus years old with several converted from coal to number 2 fuel oil.  The boilers are in need of replacement.  This will increase the efficiency of our heating system and improve our energy cost. 



 

$2,200,000       

2026

5. 

Additions to Career Academy 

Additions to the Career Academy will be based on the instructional needs of students and future programs. 

TBD

TBD 

6.

Athletic Facilities Improvements 

As determined by student need. 

TBD

TBD

   

Total estimated cost for FY2026



 

$8,950,000