This Capital Improvement Plan (CIP) provides a recommended framework for undertaking major capital improvements over the next several years. The following goals continue to guide planning and prioritization of the CIP.
- Provide a safe, healthy, and inviting learning environment for students, staff, parents, and community.
- Protect infrastructure and ensure the proper operation of all critical building systems.
- Ensure that facilities are energy efficient.
- Ensure that facilities are equipped for current instructional and administrative technologies.
Identifying facilities needs are based on input from principals and administrators, facilities staff, and a range of consultants in the fi eld. In 2021, Cornett & Cundiff, Inc. performed a survey of the roofs in the school division. In 2022-2023, Crabtree, Rohrbaugh & Associates completed a full facilities assessment to identify structural, mechanical, electrical, and plumbing needs for all school sites and assist with capital planning.
From the list of needs, major projects costing over $100,000 are included in the current CIP. As a caution, estimates should be considered place holders. The best estimates are obtained after preparation of working drawings (bid) documents and true cost is determined through the competitive bid process.
NOTE: The following timelines are hypothetical and predicated on the assumption that the division will increase its Facilities Category over each of the next several fiscal years. The following tables provide a description of projects, costs, and recommended timelines for each project. In some cases, projects are bundled for similar types of work or because of advantages related to logistics.
Henry County Public Schools Capital Improvement Plan
| Priorities |
Project |
Description/Rationale |
Estimated Cost |
Year |
| 1. |
Pavement Replacement STE and CA |
The pavement in the parking lots of Stanleytown Elementary and Career Academy needs replacement |
$1,500,000 |
2026-2027 |
| 2. |
Pavement at FCMS |
The pavement in the parking lot of Fieldale-Collinsville Middle needs replacement |
$1,250,000 |
2026-2027 |
| 3. |
Switchgear replacements at FCMS and LPMS |
The main electrical switchgear has existed since the school was built and needs replacement at Fieldale-Collinsville Middle School and Laurel Park Middle School |
$838,000 |
2026-2027 |
| 4. |
Roof coating/replacement AE |
The roof at Axton Elementary has exceeded its warranty and requires a new coating on part of the roof and replacement in other areas |
$900,000 |
2026-2027 |
| |
|
Total Estimated Cost for FY27 |
$4,488,000 |
|
| Priotities |
Project |
Description/Rationale |
Estimated Cost |
Year |
| 1. |
Switchgear replacements BHS and MVHS |
The main electrical switchgear has existed since the school was built and needs replacement at Bassett High and Magna Vista High |
$3,250,000 |
2027-2028 |
| 2. |
Boiler Replacement MVHS, LPMS, and AE |
The boilers at the listed facilities are 30-plus years old, with several converted from coal to number 2 fuel oil. The boilers need to be replaced. This will increase the efficiency of our heating system and improve our energy costs. |
$2,200,000 |
2027-2028 |
| 3. |
Renovations to Sanville |
Renovations to Sanville Elementary to include building additional classrooms |
$4,600,000 |
2027-2028 |
| 4. |
HVAC Upgrade DME |
DME- Replacement of HVAC Equipment |
$3,300,000 |
2027-2028 |
| 5. |
HVAC Upgrade GWCE |
GWCE- Replacement of HVAC Equipment |
$3,300,000 |
2027-2028 |
| 6. |
Roof Replacement DME |
DME - replacement of the EPDM roof that has been out of warranty since 2022 |
$1,375,000 |
2027-2028 |
| 7. |
Renovations to Stanleytown |
Renovations to Stanleytown to include building additional classrooms |
$11,000,000 |
2027-2028 |
| 8. |
Roof Replacement GWCE |
GWCE- replacement of the EPDM roof that has been out of warranty since 2022 |
$1,375,000 |
2027-2028 |
| |
|
Total estimated cost for FY2028 |
$30,400,000 |
|
| Priotities |
Project |
Description/Rationale |
Estimated Cost |
Year |
| 1. |
Pavement Replacement G.W. Carver Elementary |
Pavement in the parking lot at G.W. Carver Elementary needs replacement |
$600,000 |
2028-2029 |
| 2. |
Replacement of Single- Pane windows at BHS |
The single-pane windows at Bassett High School need replacement |
$1,938,000 |
2028-2029 |
| 3. |
Replacement of Lighting at BHS |
Replace lighting at Bassett High School with LED lighting |
$978,070 |
2028-2029 |
| 4. |
Replacement of Single- Pane windows at MVHS |
The single-pane windows at Magna Vista High School need replacement, and the steel lintels need to be painted |
$1,914,000 |
2028-2029 |
| 5. |
Replace all HID fixtures at MVHS |
All HID fixtures at MVHS need to be replaced with LED light fixtures |
$969,910 |
2028-2029 |
| 6. |
HVAC replacement at MVHS |
Replace all HVAC equipment at Magna Vista High School |
$6,500,000 |
2028-2029 |
| |
|
Total estimated cost for FY2029 |
$12,899,980 |
|
| Priorities |
Project |
Description/Rationale |
Estimated Cost |
Year |
| 1. |
Replacement of single- pane windows at the CA |
Replacement of single- pane windows at the CA The single-pane windows at Career Academy need replacement |
$868,800 |
2029-2030 |
| 2. |
Electrical Gear replacement at CA |
Replace all original electrical gear at Career Academy |
$317,388 |
2029-2030 |
| 3. |
Replacement Lighting at GWCE |
Replace lighting at George Washington Carver Elementary School with LED lighting |
$421,945 |
2029-2030 |
| 4. |
Electrical Gear Replacement at CCL |
Replace all general electrical gear at the Center for Community Learning |
$406,152 |
2029-2030 |
| 5. |
Replacement of the vertical heat pump at CCL |
Replace vertical heat pump and RTUs at the Center for Community Learning |
$1,200,000 |
2029-2030 |
| 6. |
Switch Gear Replacement at AE |
Replace the building's electrical switch gear at Axton Elementary School |
$2,500,000 |
2029-2030 |
| 7. |
Replacement Lighting at AE |
Replace lighting at Axton Elementary School with LED lighting |
$350,000 |
2029-2030 |
| 8. |
HVAC replacement at MOE |
Replace all HVAC equipment at MOE |
$4,000,000 |
2029-2030 |
| |
|
Total estimated cost for FY2030 |
$10,064,285 |
|
| Priorities |
Project |
Description/Rationale |
Estimated Cost |
Year |
| 1. |
Replacement of Single- Pane windows at FCMS |
The single-pane windows at Fieldale-Collinsville Middle School need replacement |
$693,209 |
2030-2031 |
| 2. |
Theatre Lighting at FCMS |
Fieldale-Collinsville Middle School requires new theatre lighting replacement |
$125,000 |
2030-2031 |
| 3. |
Roof Replacement FCMS |
Roof replacement at Fieldale-Collinsville Middle School |
$4,000,000 |
2030-2031 |
| 4. |
Replacement of Single- Pane windows at LPMS |
The single-pane windows at Laurel Park Middle School need replacement |
$1,307,304 |
2030-2031 |
| 5. |
Replacement Lighting at LPMS |
Replace lighting at Laurel Park Middle School with LED lighting |
$660,255 |
2030-2031 |
| |
|
Total estimated cost for FY2031 |
$6,785,768 |
|
| Priorities |
Project |
Description/Rationale |
Estimated Cost |
Year |
| 1. |
Additions to Career Academy |
Additions to the Career Academy will be based on the instructional needs of students and future programs |
TBD |
TBD |
| 2. |
Athletic Facilities Improvements |
As determined by student needs |
TBD |
TBD |